Sun–Fri · 09:00–18:00 NPT NEPAL · EN
ME Engineering Private LimitedME EngineeringPrivate Limited · Nepal
Food processing · Pokhara, Nepal · Completed

500 kg/hr Vertical Cross-Tube Steam Boiler - Krishna Food Production

Design, supply and commissioning of a 500 kg/hr vertical cross-tube water tube internal furnace steam boiler for food processing operations at Krishna Food Production, Pokhara.

Capacity
500 kg/hr
Sector
Food processing
Location
Pokhara, Nepal
Commissioned
Completed
01 — The Project

ME Engineering supplied and commissioned a 500 kg/hr vertical cross-tube, water tube, internal furnace steam boiler for Krishna Food Production in Pokhara, Nepal, providing a compact steam solution for the client's food processing operations.

The vertical cross-tube water tube design uses an internal furnace with cross tubes carrying boiler water through the combustion zone, giving fast steam raising and efficient heat transfer in a smaller footprint than horizontal designs - well suited to sites with limited boiler house space.

For Krishna Food Production, this meant a compact, reliable steam supply with optimised fuel consumption for food processing applications. ME Engineering handled design, supply, and commissioning, building the unit to IBR standards to ensure safe, efficient operation.

02 — Scope of Supply

What we delivered

01500 kg/hr vertical cross-tube water tube internal furnace steam boiler
02Furnace and fuel feeding arrangement
03Feed water system
04Installation & commissioning
05 — Technical Specification

Equipment & ratings supplied

Boiler type Vertical cross-tube, water tube, internal furnace
Capacity500 kg/hr
06 — Challenge & Solution
The challenge

Krishna Food Production needed a compact, efficient steam generation system for food processing applications, with reliable operation and optimised fuel consumption, likely within a constrained boiler house footprint.

Our solution

ME Engineering designed, supplied, and commissioned a 500 kg/hr vertical cross-tube water tube internal furnace boiler, delivering a space-efficient steam solution with optimised fuel use for the client's food processing operations.