+977 1 4350121 boilersnepal@gmail.comSun–Fri · 09:00–18:00 NPT NEPAL · EN
ME Engineering Private LimitedME EngineeringPrivate Limited · Nepal
Yupin International Foods - 3000 kg/hr Wood-Fired Steam Boiler Plant
Food Processing · Completed

Yupin International Foods - 3000 kg/hr Wood-Fired Steam Boiler Plant

Design, supply, installation and commissioning of a 3000 kg/hr horizontal smoke tube 3-pass wood-fired steam boiler for food processing applications at Yupin International Foods.

Capacity
3000 kg/hr Wood-Fired Steam Boiler Plant
Sector
Food Processing
Commissioned
Completed
01 — The Project

A 3000 kg/hr horizontal smoke tube 3-pass wood-fired steam boiler designed to generate steam for food processing operations. The boiler converts the heat from wood fuel into saturated steam used in production processes, delivering reliable and energy-efficient steam generation for industrial applications.

ME Engineering supplied and commissioned the complete boiler system, including auxiliary equipment and steam distribution components. The 3-pass smoke tube design improves heat transfer efficiency and fuel utilization while ensuring dependable operation and ease of maintenance. The project supports the client's production requirements with a robust and cost-effective steam solution.

02 — Scope of Supply

What we delivered

013000 kg/hr smoke tube steam boiler
02Feed water tank and pumping system
03Steam and condensate piping
04Safety valves and mountings
05Installation and commissioning
Yupin International Foods - 3000 kg/hr Wood-Fired Steam Boiler Plant equipment
06 — Challenge & Solution
Before
The challenge

The client required a reliable and fuel-efficient steam generation system to support continuous food processing operations while utilizing locally available wood fuel.

Our solution

ME Engineering delivered a 3000 kg/hr horizontal smoke tube 3-pass wood-fired boiler system with complete auxiliaries, ensuring efficient heat transfer, stable steam output and dependable plant operation.

Planning a steam plant?

Tell us your steam load & fuel — budgetary quote in two working days.