CS Fabric - 6000 kg/hr Steam Boiler Installation & Commissioning
Fabrication · Biratnagar · Completed

CS Fabric - 6000 kg/hr Steam Boiler Installation & Commissioning

Supply, installation and commissioning of a 6000 kg/hr steam boiler system for an industrial fabrication facility to ensure reliable steam generation and efficient plant operation.

Capacity
6000kg/hr
Sector
Fabrication
Location
Biratnagar
Commissioned
Completed
01 — The Project

A 6000 kg/hr steam boiler plant designed to generate steam for industrial process applications in a fabrication facility. The system provides reliable steam generation for production processes while improving operational efficiency and ensuring safe boiler operation.

ME Engineering carried out the supply, installation and commissioning of the steam boiler system, including auxiliary equipment and site integration. The project was executed to deliver dependable steam production, simplified maintenance and long-term operational reliability. Our engineering team ensured proper installation, testing and performance verification before handover to the client.

02 — Scope of Supply

What we delivered

016000 kg/hr steam boiler
02Feed water tank system
03Boiler mounting and accessories
04Chimney and ducting system
05Installation and commissioning
CS Fabric - 6000 kg/hr Steam Boiler Installation & Commissioning equipment
05 — Technical Specification

Equipment & ratings supplied

Steam generation capacity6000kg/hr
Boiler typeSteam boiler
06 — Challenge & Solution
Before
The challenge

The client required a reliable steam generation system integrated into existing plant operations while minimizing installation downtime.

Our solution

ME Engineering supplied and commissioned a 6000 kg/hr steam boiler system with supporting utilities and site integration to ensure safe and efficient operation.

07 — Results
Reliable steam supply · Production support · Continuous plant operation Improved efficiency · Boiler performance · Optimized steam generation